I'm a new user and I'm facing diffultives in activities setup.
I've just created an activity with an estimated workload of 6 days.
This activity has been assigned to one member (100% capacity on the project).
I expected to see on the planning view a 6 days bar.
But the activity appears with a duration of one day.
Furthermore, in the activity view, in the 'planned days' column, only one day is indicated.
I don't understand why.
Could you explain me ?
Thanks,
Can you verify the "capacity" of the resource " Thirion Lannister " ? ( he died on the episode 3 *joke*)
He can do few days ( depend of capacity ) in one day . You can have more detail of this in Report->Planning->Monthly Planning resource/project/activity .
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.