is it possible when you book time at ‘real work allocation‘ for the first time for an activity that the status will automatically be set to ‘in progress’? Because normally if you have no more time left, the status will be set with the last booking to ‘completed’.
And we also have one resource, a project service who has also to book time for some projects. If there is no more time left or he set the left time to 0 the activity gets not automatically to ‘completed’ but to ‘cancelled’. As we know this happens only at this one project service. But sometimes if he is allocated as project team to an activity it worked that the status was set to ‘completed’. Can anybody explain why this happens? In the workflow it is possible to set from ‘in progress’ to ‘completed’. And also at other resources it works as it should.
By the way we are using the version 6.4.1
is it possible when you book time at ‘real work allocation‘ for the first time for an activity that the status will automatically be set to ‘in progress’?
Yes, this is default behavior. You'll see a small green flag that will inform you about the change.
This automation can be disabled in global parameters screen (tab "work")
Because normally if you have no more time left, the status will be set with the last booking to ‘completed’.
This is also available, and set as default behavior. You see a "finish" flag, but it may be stiked if move is impossible (for instance if result is required and not set)
This automation can also be disabled in global parameters screen (tab "work")
And we also have one resource, a project service who has also to book time for some projects. If there is no more time left or he set the left time to 0 the activity gets not automatically to ‘completed’ but to ‘cancelled’.
Because in your workflow, it is the fist status for the corresponding profile that will check item as "done"
is it possible when you book time at ‘real work allocation‘ for the first time for an activity that the status will automatically be set to ‘in progress’?
Yes, this is default behavior. You'll see a small green flag that will inform you about the change.
This automation can be disabled in global parameters screen (tab "work")
This works now. But there is no check in the box and date of handled. Is this a bug? Or is this normal?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.