Hello all,

is it possible when you book time at ‘real work allocation‘ for the first time for an activity that the status will automatically be set to ‘in progress’? Because normally if you have no more time left, the status will be set with the last booking to ‘completed’.


And we also have one resource, a project service who has also to book time for some projects. If there is no more time left or he set the left time to 0 the activity gets not automatically to ‘completed’ but to ‘cancelled’. As we know this happens only at this one project service. But sometimes if he is allocated as project team to an activity it worked that the status was set to ‘completed’. Can anybody explain why this happens? In the workflow it is possible to set from ‘in progress’ to ‘completed’. And also at other resources it works as it should.
By the way we are using the version 6.4.1

Thanks and regards.

Please Log in or Create an account to join the conversation.

More
20 Oct 2017 23:19 #2 by babynus

is it possible when you book time at ‘real work allocation‘ for the first time for an activity that the status will automatically be set to ‘in progress’?

Yes, this is default behavior. You'll see a small green flag that will inform you about the change.
This automation can be disabled in global parameters screen (tab "work")

Because normally if you have no more time left, the status will be set with the last booking to ‘completed’.

This is also available, and set as default behavior. You see a "finish" flag, but it may be stiked if move is impossible (for instance if result is required and not set)
This automation can also be disabled in global parameters screen (tab "work")

And we also have one resource, a project service who has also to book time for some projects. If there is no more time left or he set the left time to 0 the activity gets not automatically to ‘completed’ but to ‘cancelled’.

Because in your workflow, it is the fist status for the corresponding profile that will check item as "done"

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
24 Oct 2017 10:26 #3 by #Chris
Thanks for your help.

is it possible when you book time at ‘real work allocation‘ for the first time for an activity that the status will automatically be set to ‘in progress’?
Yes, this is default behavior. You'll see a small green flag that will inform you about the change.
This automation can be disabled in global parameters screen (tab "work")

This works now. But there is no check in the box and date of handled. Is this a bug? Or is this normal?

Attachments:

Please Log in or Create an account to join the conversation.

More
25 Oct 2017 11:02 #4 by babynus
It depends on configuration of your status.
The status must "check handled"

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: #Chris

Please Log in or Create an account to join the conversation.

More
09 Nov 2017 12:06 #5 by #Chris
we have in the status checked handled

and also set in the global parameter the "set to first handled / done status" to yes


But still there is no automatically check in the box at handled or done if we book time at ‘real work allocation‘. And also no date will be set.
Attachments:

Please Log in or Create an account to join the conversation.

More
09 Nov 2017 13:46 #6 by babynus
On activity type, set handled as locked to ensure it is automatically set from status and never manually changed.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: #Chris

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.073 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.