30 Oct 2017 15:24 #1 by saran
Hi,

we have purchased screen customization and we are unable to add column field in "Real Work Allocation" screen. Please guide us on it.

We need a column to update the percentage completion on each activity by individual resource while they enter Real work allocation and start time & end time for the same. A report also need to be generated on weekly basis for the specific activities on resource basic in that specific activity.

Thanks in Advance,
Saran

Please Log in or Create an account to join the conversation.

More
30 Oct 2017 17:09 #2 by babynus
You cannot customize Real Work Allocation screen with screen customization plugin.
It can customize "alomosté every screen, but not all : not real work, not planning, not topday, ...
Only screen with design with List / Detail, not including parameters screen.

But what you try to do is useless.
When you have assigned work on activity, and enter real work (and possibly reasses left work) you will automatically have completion calculated : % completion = real / (real + left)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.