23 Nov 2017 20:22 #1 by Amaro
Hi , excelent tool you have made

Im stuck on this , its very simple i think. Let say that i have two activities 1 and 2, the second activity must start after the first activity finish. At first both activities have the same start date, then when I add activity 1 as predecesor of activity 2 , what happens is that activity 2 get updated but only end date but the start date remains unchanged. I've performed the same case in PROJEQTOR online demo and it works as espected but local installation does not. In online demo when relate activity 2 has sucesor of activity 1 , the activity 2 has to be moved in gantt view to start after activity 1



thanks for any IDEAS , is it a bug or config missing


best regards
German
Attachments:

Please Log in or Create an account to join the conversation.

More
05 Dec 2017 19:32 #2 by babynus
1) recalculate the planning (gear button)
2) Add some assigned work, or set planning mode as "fixed duration"

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 3.011 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.