Sometimes, planned end date is set before the planned start date, which prevent any further update on the concerned activity.
I'm currently using v6.2.5.
Here is a step by step method to generate this bug:
- Create an activity (just set the name, no date). It will appears on the current day (date D) on the planning.
- Run planning calculation a day before (D-1). Planned start and end date will be set to D-1.
- Update the field "handle" on the activity and set it on current date (date D).
- Run again a planning calculation
From here, you got an activity with a start date > end date which cause the bug.
Regards,
Quentin.
How this can be fixed on the interface ? The only known possibility (to me) is to update the field in the database.
I followed the tutorial to update projeQtor version but the bug is still present.
When I logged in with admin account, i get the pop up with the 6.4.4 update notification, but I still read ProjeQtor 6.2.5 on the bottom right.
Ok my bad, I haven't updated the right directory.
Now in 6.4.4, the bug is still alive (still possible to get a start date > end date) but the Activity can be updated.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.