Dear, I'm using Projeqtor version 6.3.7.
I created one project with 2 subproject with each one some activities and tasks.
I set last week the master project start date with 1st December 2017. Today I need to change this date to 15 December 2017 and accordingly every start date in sub projects and activities/tasks.
I believe it was enough edit Start Date in master project, but it doesn't work. Planned date does not change.
Why?
Sub project are set with status "In progress" for my mistake, is this the problem? I could not change it to "Recorded".
Planned dates do not take into account valaidated start date : it is just a date to control that project starts when expected, not a constraint.
To add a constraint, add a fixed milestone and dependencies.
Then moving the milestone will move the projet tasks
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.