Assignment - Start Date and End date

More
12 Dec 2017 09:07 - 12 Dec 2017 09:07 #1 by saran
Hi

On Project level resource allocation the "Start and End" dates are provide but when it comes to Assignment on a particular task/ activity, we need a start date and end date to be given, in order to track how the resource are engaged with task.

Whether this can be customized.

Kindly help on this.

Thanks in Advance.
Saran
Last edit: 12 Dec 2017 09:07 by saran.

Please Log in or Create an account to join the conversation.

More
12 Dec 2017 10:19 #2 by babynus
Start date for assignement will be determined by planning calcuation from :
- planning mode of activity
- validated dates of activity (for some planning modes, not for default "asap" planning mode)
- dependencies of activities
- resource capacitty and availability

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.