My question is how to make the change of status to an activity that has been closed.
My problem occurs on an activity having as status "Save", it was placed in "Done", now it is no longer possible to return to "Save".
How to solve the problem?
The planning date for this activity has also changed as a result of this change.
The scheduled start date and the planned end date are the same day when it was not the case just before.
This creates a malfunction on the schedule.
When you do not have an authorization to change one status to another one it is a Workflow problem. Perhaps you have to use an intermediate status.
Check your workflow screen.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.