10 Jan 2018 09:54 #1 by apad
mass assignment was created by apad
Hi

Is there a way to assign a ressource on all activities of a project in "one click" ?
Imagine a project with more than 100 activities / sub-activities / sub-sub-activities.
I affected a ressource to the project, hoping activities will inherit affectation but no.
Have I to link each activity with ressource one by one ?

Regards

Please Log in or Create an account to join the conversation.

More
10 Jan 2018 14:50 #2 by babynus
Replied by babynus on topic mass assignment
It's not possible afterwards the way you expect it.
What is possible with global parameters is :
- automatically set responsible only resource on mono-allocated projects
- auto assign responsible to activity

What you can do is use multiple update mode to set responsible after setting the global parameters.
Then your resource will automatically be assigned to all changed tasks.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
11 Jan 2018 09:28 #3 by apad
Replied by apad on topic mass assignment
Thank you.

Ok I tried what you proposed. I succeeded for mono-allocated project.
But for multi-allocated projects, I understand that I have to assign activities one by one (except for the responsible) for each resource.
I had a look on import possibilities but I found nothing. Do you confirm that it's not possible to import assignation ?

Regards

Please Log in or Create an account to join the conversation.

More
11 Jan 2018 15:34 #4 by babynus
Replied by babynus on topic mass assignment
Assignment CAN be imported, but it's not as easy as importing Activities, because you cannot export assignments to get a template.
Go to import feature, you'll see Assignment is proposed for import.
Click on help icon beside element selector for help on expected format.
It is quite technical :
idProject = id of the project
refType = 'Activity' for activities
refId = id of the activity (you can for instance export Activities to get their ids)
idResource = id of the assigned resource
idRole = id of the function of the resource on the activity (will determine cost)

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: apad

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.