I am trying to check if I can follow my project cost with this wonderful tool.
I set a cost to my resource.
Now I would like to give him an higher salary
So let say the first cost is 100 euro per day, and from 2011/11/01 the cost will be 150.
I wonder if I can do that. There is a "start date" in the "resource cost" form, but the role of this entry is not clear to me.
Moreover, this entry is disabled.
Is this possible to change the cost of a resource from a given date, and if so, how may I do it ?
Hi,
Start date is exactly what you are looking for.
For first cost it is disabed.
For others, it is mandatory.
All is explained in the user Manuel (just hit [F1] key :cool:)
Hi
Thanks. I had check in [url]http://127.0.0.1/projectorria/manual/manual.php[/url] before asking but was unable to find the answer.
(I use projectorria V1.7.2). Is it in the activity section ?
I confirm : it was not included in V1.7
Manual has been largely completed (and finished) in V1.8.
So you can refer to online manual to get the latest version.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.