Hi,
In Progress section (project panel) I want to manage my project, upon its Planned Date and Real Date.
I Dont' want to let the System calculate the validated Date automatically according to the entree Day Date, unless I enter it, manually. I Want to have full control of the validated Dated.
I Love ProjeQtOr , but How to setup the calculation of the Project's Date(s), because there is too much date(s) to manage in ProjeQtOr. !!!
we are missed up and mixed up with all the Dates !!
Validated = initial baseline (not calculated, manually entered or automatically copy from planned through planning validation button)
Planned = Calculated from wontrintes you gave (work, dependencies, planning mode)
Real = from Real work Allocation (first entered day = start, last entered day when no left work = end)
Requested = requested by customer (not often used)
Luckily we hide "latest" which are calculted to define critical path.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.