You can modify real work allocation unit from days to hours.
To do this, go in global parameters screen, section work time then go down to unit for work.
Conversion is done automaticly. I suggest you to do this operation, just and if possible before the begining of the project, to be sure that everybody use the same base of work allocation all along.
you can change the number of hour per day as you want, nine for instance.
Also, if your resource works 9 hours and not 8 as planned , you can impute 9 h on his imputation time table, a red color will indicate this anomaly at the bottom of the column.
As well, no worries about conversion.
You're welcome.
is it possible to charge more than the number of hour in a day. I mean if i set 8h by day. is it possible for a ressource to charge 9h for a day ?
Yes, you can input more that 8hours per day even if you define 8 hours per dayn exactly as you can enter more thant 1 day per day if you enter work in days.
But planning will always paln only 1 day per day, so 8 hours per day
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.