Hello,
In the work input screen i've gto a sub project with 3 activities. Why do i get the first activity in grey and with a "-" button near it while it's just a simple activity with no sub activities link to it
in this exemple the sub project is 1- Lot unique and sub activities are Ananlyse du besoin, spécification and conception. why do i get Analyse du besoin in grey ?
Hello,
I think you get "Analyse du besoin" in grey because it is a parent Activity.
You should look in your Activity "Spécification" and "Conception" the field parent Activity. If it is, remove ""Analyse du besoin" like parent activity.
Are you sure "Analyse du besoin" is not a parent activity of an other activity without assignment ? Can you screen your wbs columns of activities and click on show close items please.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.