Then it proceeds to cover the other three types (SS, SF, FF).
For SS, it recommends a workaround of adding a milestones for both tasks.
While this is correct, in a normal project, usually there would be a predecessor task that serves the same purpose.
In that case there is no need for a milestone.
I think this needs to be pointed out.
The help should also point out that without a milestone or predecessor task, the activities would typically launch in "ASAP" mode (delayed only the availability of their respective resources), rather than being launched together.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.