Hello,
I got a resource "rA" wich is also a user "uA".
"uA" is Project leader,
"rA" belong to a team "tA", and has 2 projects "pA" & "pB"
"tA" is made of 4 other resources/users (rB, rC, rD), the team manager is my resource "rA"
I'd like "uA" to manage real work allocation for all members of her team ... please tell me how ?
Default configuration sets it working as you wish : project leader can manage real work of resources allocated to his projects.
This is managed through "specific access rights"
But my purpose is to allow a team manager to change real work allocation for all members of it's team even if this manager is not project leader !
It'll be more easy for me to explain that in French ... sorry
members of accountancy team are working on several projects, but team manager is not project leader on those projects.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.