Interdépandance

More
30 May 2018 13:29 #1 by Mike007
Interdépandance was created by Mike007
Hi,

how to mark the interdependence between two projects?

Thanks

Please Log in or Create an account to join the conversation.

More
30 May 2018 14:20 #2 by alainforma
Replied by alainforma on topic Interdépandance
hI,

The solution would be to create a project X or Y, and then to consider that these two projects are each one an activity therefore linked by the "interdependencies". ( by the way, which ones?)

Please Log in or Create an account to join the conversation.

More
30 May 2018 21:14 #3 by babynus
Replied by babynus on topic Interdépandance
You can create dependencies
- from project A to project B
- from project A to activity of B
- from activity of A to activity of B

You just have to have rights on both projects

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
01 Jun 2018 11:46 #4 by NarayanAras
Replied by NarayanAras on topic Interdépandance
Here's the "how" part:

Go to the Projects screen. Click on the project you want.
Now scroll down in the bottom half of the screen.
Select the Predecessor element or Successor element section (depends on what you want).
In the table below, click on the green plus sign. A pop-up appears.
Select the type of element (project, activity, meeting, milestone, etc.)
Specify the delay between them, and the type of dependency. Press OK.

This works for the first two options Babynus explained.

To set a "Activity in the current project -> another project" type dependency, select the Planning screen.
In the top half of the screen, select the activity.
The lower half of this screen shows the same Predecessor element and Successor element sections.
Set up your links exactly as explained before.

Please Log in or Create an account to join the conversation.

More
04 Jun 2018 12:44 #5 by babynus
Replied by babynus on topic Interdépandance
Thanks NarayanAras for this detailled explanation.

I would just add it is possible to "draw" a dependency in the Gantt chart with Drag & Drop :
- click on predecessor bar,
- hold the button and drag to the successor bar.
A dependency line will be shown in blue, as a proposal.
- Drop (release button) to validate the creation of the dependency.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
04 Jun 2018 13:17 #6 by NarayanAras
Replied by NarayanAras on topic Interdépandance
I considered that, but then we don't have a Gantt chart that shows multiple projects and their tasks.
So IINW this trick is only usable to establish dependency within a project; but it cannot cross the boundary of a project.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.