ProjeQtOr free project management software - Start a task from milestone - ProjeQtOr
 

Start a task from milestone

More
20 Nov 2011 14:30 #1 by bailleulthierry
Hi,

In first time, sorry for my poor english...

My problem is :
- I created a milestone "fixed date" A
- I created task B with predecessor milestone A
When I calculate planning the task B is not planned after milestone A.

Thanks

Please Log in or Create an account to join the conversation.

More
20 Nov 2011 15:36 #2 by babynus
Hi,
This is clearly a bug.
Registered as ticket #476.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.