First of all, congratulations for such a great job. Very impressed after few days testing Projeqtor.
Right now I am using the Project Templates. I have create the TemplateX project, and add different activities with a validated start and end dates.
My question now is:
If I copy the TemplateX to a RealX project, how could I update automatically the dates of the activities upon to the current date?
I tried to link the activities with the predecessor option, to see if just changing the first activity date everything would change automatically, but not success...
If I copy the TemplateX to a RealX project, how could I update automatically the dates of the activities upon to the current date?
You should not plan with validated dates.
Best is to plan activities with workload assigned to resource, but you can also plan with "fixed duration" planning mode.
Then you have at start one single milestone (start) with "fixed" planning and defined validated date. You change just this date and run planning calculation.
That's all.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.