When you create an activity and save over a validated set of date ranges for example a week, and then change the status to assigned for example this then changes the Gantt to be the date you changed it to.
This doesn't help too well with planning, i tried changing the planning dropdown box to fixed duration and some others but this doesn't do anything and it still changed the gantt chart and assigns the validated dates into planned which in this example would become todays date.
Is there no way for the Gantt to just show validated dates?
Hello,
On the Gantt chart, ONLY calculated dates are displayed.
These calculated dates can sometimes be identical, and whatever the chosen planning method, to validated dates. Keep in mind that they have been approved by calculation before being displayed (or not) on Gantt.
For more information press F1 on gantt chart screen
Best regards
ProjeQtOr mainly uses "effort driven" calcuation.
So activities with no work assigned are not really calculated, except for "fix duration" planning mode.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.