I'd like to know if it's possible and how to do when :
- you began to work about an activity
- you encounter a problem needing a decision from an external actor - and you don't have any clue when he will take this decision
- so you want planning calculation to not schedule the activity any more (hopefully not endlessly
I've tried to put a milestone in the future and a dependency to the activity, but as far as I've seen it doesn't impact the activity scheduling when there's already some work done.
ProjeQtOr will work as you expect :
Here is an example of an activity with predecessor milstone, but real work already started : the left work is correctly planned after the milestone
Of course, gantt bar starts at real start date, but left work is planned as expected
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.