Automatic calculation

More
08 Jan 2019 10:28 #13 by sogeti
Replied by sogeti on topic Automatic calculation
Here is what I have.

Attachments:

Please Log in or Create an account to join the conversation.

More
16 Jan 2019 11:03 - 16 Jan 2019 11:16 #14 by sogeti
Replied by sogeti on topic Automatic calculation
Hello,

I have other news about the automatic calculation of our projects.
I have cancelled the automatic calculation and put it back.
The planning of our project named "TEST" has been calculated on Monday 7PM as requested.
Next, I've decided to make another try and have changed the date of our project "TEST". Also, I have created another project named "TEST 2" to see if it will work.

On Tuesday at 7PM, "TEST" has been modified automatically but not "TEST 2". Each data has been entered the same way in both projects but it doesn't work the same way.
Both of them are in the logs.
I will try during all the week to see if it will work for "TEST" and "TEST 2".

Have you already have this type of feedback from other users ?

I am looking forward hearing from you,
Regards
Last edit: 16 Jan 2019 11:16 by sogeti.

Please Log in or Create an account to join the conversation.

More
16 Jan 2019 19:19 #15 by babynus
Replied by babynus on topic Automatic calculation
Do the project have
- same Project type ?
- same allocations ?

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
17 Jan 2019 10:09 - 17 Jan 2019 10:10 #16 by sogeti
Replied by sogeti on topic Automatic calculation

same Project type ?

Yes

same allocations ?

Yes

Do you think it can come from the fact that we created the project "TEST 2" after putting the parameters of automatic calculation ?
Last edit: 17 Jan 2019 10:10 by sogeti.

Please Log in or Create an account to join the conversation.

More
17 Jan 2019 11:05 #17 by babynus
Replied by babynus on topic Automatic calculation
Can you try and restart the CRON system ?
Are the two projects correctly calculated ?
If it works, it may be an access rights issue ...

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
18 Jan 2019 09:18 - 18 Jan 2019 09:34 #18 by sogeti
Replied by sogeti on topic Automatic calculation
I have done what you suggested and it works now.
I have checked on 4 projects and they have been calculated automatically.

So we have to restart the CRON system after changing the parameters ?

EDIT : Actually, I have checked on another project that has been created at 5:37PM but it has not been calculated (knowing that the automatic calculation is at 7PM). It has the same type and the same team of others.
Last edit: 18 Jan 2019 09:34 by sogeti.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.049 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.