Great product, overall very functional. One thing i can't figure out, though, is how to plan for periods where resources have to work overtime to complete an task within a fixed period. Typically this involves a service engineer that has to travel to a remote site for commissioning, and has access to the factory during a set period, i.e. two weeks. During this period the engineer typically works 12 hours+ per day, but never more than the quoted amount of hours the client has paid for. If I allocate the quoted amount of hours into the resource allocation for the task, the planner will prolong the task period to "expend" the hours using the normal working hours (7.5h), which is logical, but in my scenario not what i really want it to do, as the engineer only has two weeks access to the factory.
What is the recommended way of handling scenarios like these in ProjeQtor?
One solution is to change the capacity of the resource.
But this will be valid everytime, not only on a specific time.
Another solution is to deal with pool.
Create a pool with the resource and an fake resource with capacity as extra.
Then assign the pool to the activity.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.