ProjeQtOr free project management software - Resource planning issue with resource pool - ProjeQtOr
 

Resource planning issue with resource pool

More
07 Jan 2019 07:49 #1 by failman
Hello,

When adding resources to a resource pool, and using said resource pool in an activity for doing work, the resources that are part of the resource pool appears to be free during the period where they are working in the resource pool when viewing them in the resource planning/resource reports.

Is there a way around this? It makes resource planning confusing when using resource pools as individual resources appear to be free, but in reality is not.
Attachments:

Please Log in or Create an account to join the conversation.

More
07 Jan 2019 17:12 #2 by babynus
Yes, it is the limit of the pools.
You cannot say which resource will work on work planned for the pool.
So all appear free, even if one will have to work for the pool.
That's why we show the pool when showing data for a resource (for instance in Resource planning)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
07 Jan 2019 22:29 - 07 Jan 2019 22:31 #3 by failman
I get your point, but what if I have a pool of three resources, and assign this pool to a big task (> 1000 hours), with FTE = 3. The resources have other assigned tasks on other projects that always has higher priority than the big task, such that the work-throughput of the pool isn't necessarily 300% at all times. After executing the plan-algorithm, the big task gets scheduled based on the available work-load of the pool, and as such is aware of which of the 3 resources that are working for the pool at any given day to make this schedule happen/valid. Wouldn't it at least make sense to represent the work-hours for the pool per resource in the "Colored monthly resource planning" report, as the resources has actually been planned to do this work for the schedule to be valid, and are at least temporarily occupied?
Last edit: 07 Jan 2019 22:31 by failman.

Please Log in or Create an account to join the conversation.

More
07 Jan 2019 22:39 #4 by babynus
This could be possible, but it's heavy work and would work only in this case...

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.039 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.