I currently test the use of ProjeQtOr. It's possible to create a link with a delay.
But when I want to overlap 2 activities: it seems it's not possible that a negative delay is taken into account ?
Overlapping is possible by specifying a negative number. However, this does not mean that planification will necessarily take this into account, First of all, calculation depends on ongoing priorities and availabilities of resources.
Perfect. Indeed after making changes, the automatic calculation is done automatically only if the user is on the planning screen and the box is checked. Otherwise from another screen even if the box is checked, you have to manually restart the calculation by clicking on the main button after coming back to this planning screen. This protects against inappropriate recalculations.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.