Witch ressource to handled the new project

More
16 Jan 2019 15:51 #1 by LaurentCap
Hello,

I have a team of 4 ressources. They manage 158 projects.

They have made the WBS with either fixed and floating milestones.
To proceed so In addition of the fixed delivery date, I've made a priority list for the "ASAP" projects.

So I now know the estimative delivery date of all the projects. It's GREAT.

But, with new weeks comes new projects.
Does ProjeQt'Or give a tool to "insert" a new project in the planning ?
Or more concrete how do I proceed to "insert" new projects with the best choice of the ressource ?

For the moment, I think that I must extract the floating milestone project list of each ressource and set the new project priority.
Then, I have to ask the ressource to run the planning with the new project to have the best calculated delivery date.
Have to do the same with all the ressource and choose the one with the best delivery date.

Is this solution the only one existing in ProjeQt'Or ?

Thanks for your help.

A ProjeQt'Or fan.

Please Log in or Create an account to join the conversation.

More
16 Jan 2019 16:26 #2 by babynus
No, there is not "best choice" proposition.
First because it is quite complex, but also because only Project Leader can know if a resource is able to execute a task.
We don't hav competency management so that you can specify the competency required for a task and then have proposition of competent resources.

Possibly, instead of changing resources, you can first have a look at availability reports to check whick resource has more "available" timeslots.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
16 Jan 2019 16:47 #3 by LaurentCap
Thanks for your reply.

I will effectively choose the ressource for the competence he own. Sometimes it's hard because I have ressources with same knowing.

Instead of have a look on reports, because ProjeQt'Or fullfile the agenda of each ressource (they plan the projects with floating milestones in planning mode "ASAP") is there a simulated planning mode ?
A function to launch planning with a ressource to view the result and a button to transpose in the ressource planning if simulation accepted.

Thanks for your help.

A ProjeQt'Or fan.

Please Log in or Create an account to join the conversation.

More
16 Jan 2019 19:20 #4 by babynus
No, ProjeQtOr has no simulation capacity.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: LaurentCap

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.034 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.