I can not close an activity, I put the date but the chek box is not enabled. I need to run something?
When scheduling the activities of a person I would like to take into account the date of termination of the above; only I can do through validation dates; no other way that validates dates precedence?
The "closed" checkbox is disabled because it must be changed through Status.
When you change Status to new status with "is closed status" checked, closed is automatically checked.
You can enable manual change : go to the corresponding Activity type and uncheck "lock closed".
About dates precedence, you just have to add dependencies (prececessors/successors).
This can be done on the activity on with drag & drop on the gantt planning.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.