03 Jul 2014 18:35 #1 by Marce386
Closed activities was created by Marce386
Hello Babynous

I want to close an activity, but the actual time is less than allocated. How can I close without having to modify the execution rate of 100%? :whistle: :whistle:
The topic has been locked.
More
03 Jul 2014 20:46 #2 by climb4fun
Replied by climb4fun on topic Closed activities
Hi Marce,

check, if you have an open work in the assignments.

Regards,

Klaus
The topic has been locked.
More
04 Jul 2014 10:17 #3 by babynus
Replied by babynus on topic Closed activities
To close an activity, you must have left work = 0.

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
More
08 Jul 2014 17:30 - 08 Jul 2014 17:55 #4 by Marce386
Replied by Marce386 on topic Closed activities



Hello babynus

If I understand you: to close an activity should be time left (d) = 0, Is saying I should change the time assigned and leave same the time left (d)?.
So how I can verify that an activity was assigned longer time than the time assigned if I should change the time?
Attachments:
Last edit: 08 Jul 2014 17:55 by Marce386.
The topic has been locked.
More
08 Jul 2014 18:03 #5 by caccia
Replied by caccia on topic Closed activities
Hi !

It's only the "left work" you should set to 0 => nothing left to do, but that doesn't change anything to the original assignment (so "assigned work" is not modified).
Best to do this in the "real work allocation" screen : enter the time spent, and review the estimated time left, but no change to the assignment.

Cheers :)
The topic has been locked.
More
11 Jul 2014 22:30 #6 by Marce386
Replied by Marce386 on topic Closed activities
hi all

If the time assigned is not equal to real time, the activity can not be closed, because only when time left = 0 the activity is left in place state closed. I need to stay in the state closed to not be displayed in the Gantt. And only in the closed state does. In state done is still seen in the Gantt. For this reason I have to modify the time assigned

Marcela
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.055 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.