View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Support us on Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Planning seems not working anymore after upgrading to 4.5.3 - Page 2 - ProjeQtOr
 
 

Planning seems not working anymore after upgrading to 4.5.3

More
08 Jan 2015 11:10 #7 by jphuart
I'm doing this as user that has admin privileges on all projects.
I'll keep in mind the access rights, because it's strange that there are no error messages issued.
The topic has been locked.
More
08 Jan 2015 18:34 - 08 Jan 2015 18:36 #8 by jphuart
Hi,

thanks for the remarks, I've found where was the problem, or at least part of it.

I have created "internal" projects for each of my clients so I can easily edit my invoices for each of them at the end of the month.
Then I have "time & materials" subprojects of these "internal" projects and I create activities inside these subprojects.
Until now I was declaring rates of affectation of resources only for the subprojects, while they were at 0% for my "internal" parent projects. Until now this was working fine, but for the last upgrade the calculation of planned work was providing a null result. Just giving a proper rate to affectation for the parent projects has solved the problem. Now planned work seems to be correctly calculated again.

Any suggestion to better understand such behaviour is welcome.
Ciao

Jean Pierre
Last edit: 08 Jan 2015 18:36 by jphuart. Reason: simplify explanation
The topic has been locked.
More
08 Jan 2015 18:59 #9 by babynus
Hi,

You put the finger on the correct origin of the issue.
In V4.5, the affectation rate determination has changed because it now takes into account start and end dates of affectations.

The fact is that % rate is a limitation that is controlled on sub-project and top-projects.
So, the applied affectation rate limit on each sub-project cannot be more that rate on top project.
So, having rate of 0% should have brought the issue on previous versions, but this was possibly a bug that new functionality fixed.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: jphuart
The topic has been locked.
More
16 Jan 2015 02:56 #10 by udirect61
Planning calculation is done in /model/PlannedWork.php, method plan().
And it works fine.
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.050 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.