I have an issue since last update for project status. When i create a meeting and close it, the status of the project is modified with meeting status.
For example, Project Alpha, status is: In progress
I create a live meeting (affected to project Alpha), realize the meeting and close the meeting --> status = Close
The status of the project alpha is modified to closed.
Plugin version of Livemeeting = 1.4
Projeqtor version: 8.2.2
No worry ,this is not an issue and it is not your plugin. It is your configuration.
You have to check in your global parameters -> activity -> automation -> auto set parent activity status -> yes.
When you activate this parameter :
If you have only one activity ( or meeting ect ..) to your project, with this parameter your project status will change according to your activity.
If you have many activities your project status will change when all activities will have the same status if the workflow allow it.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.