For example, I have two activities ( A and and the dated is list as follow. A is the predecessor of B.
Activities A:
requested Validated
starte date 2011/11/01 2011/11/01
End date 2011/11/07 2011/11/07
Activities B:
requested Validated
start date 2011/11/08 2011/11/08
End date 2011/11/10 2011/11/10
The question is when Activities A change its Validated start date to 2011/11/04 and End date to 2011/11/10. The Activities B won't change automatically. As I expect, the Validated start date of Activities B should be changed automatically to 2011/11/11 and End date shoule be 2011/11/14.
Thanks for your answer. May I ask one more question? planned date is read only. How this value be calculate? In my project, planed date seldom appear. In many times, planned date didn't show up.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.