In 8.4.0., re-calcing the plan causes failures of many Activities which cannot be scheduled. The error is: "There is ... days left to plan after resource allocation end date"
After analyzing it, I found that the problem stems from that resource allocation to projects does not get inherited properly.
Normally, a person/resource is allocated to a project if he is allocated to that project or to a parent.
However, in 8.4.0., for a resource to be properly allocated to a project for planning, he needs to be allocated to that project directly, and to every parent on the chain.
I do not think it is intentional.
Does anyone else see this phenomenon?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.