Working time vs activity's responsible/pool of ressources

More
20 May 2020 07:58 #1 by fmartin
Good morning,

i have noticed that when you assign a pool of ressources to an activity with x days, the working time spreadsheet gets wrong when the responsible of the activity is within the pool of ressources.

It seems that if the responsbile of the activity is within the pool, it does not take it into account and create automatically a new line on the assignation for the responsible.

Therefore, the calculation gets wrong as I want to assign X days to the pool and that's it. I don't want that line to interfere with the assignation.
The topic has been locked.
More
20 May 2020 08:56 - 20 May 2020 08:57 #2 by alainforma
hi,

A solution consist on going to "global parameters" then "activity" then " automation" and choose "no" at the line "auto set responsible if single resource"

Best regards
Last edit: 20 May 2020 08:57 by alainforma.
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.039 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.