It happened some time ago (in 8.4.6) but I haven’t got any time to report it, sorry.
I have 2 projects with subprojects for each :
- Project A
- Sub-Proj A.1
- Sub-Proj A.2
- Project B
- Sub-Proj B.1
- Sub-Proj B.2
They therefore appear in this order in the timesheets (which is great) with the associated activities.
A.2 is a particular subproject : it is a modification campaign and therefore mentionned as «under construction» ... in the timesheet the ressource can access activities of A.1 (normal), cannot access activities of A.2 (normal), cannot access activities of B.1 nor B.2 (definetly not normal).
I guess it’s just a gui issue. The workaroud is to unset the «under construction» checkbox of A.2, but it’s not very clean.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.