[SOLVED] Unfound left work on a task

More
03 Feb 2021 11:29 #1 by louisc
Dear team,

I have an old task that I can't close, due to the fact that Projeqtor is reporting left work that doesn't exist (or that I can't find).
The task has no subtask :
 

Do you have any idea how to solve that issue ?

Thanks !
Attachments:

Please Log in or Create an account to join the conversation.

More
03 Feb 2021 14:19 #2 by louisc
Replied by louisc on topic Unfound left work on a task
Hi again,

I have an other task with similar problem. Once again, only 1 ressource assigned to the task, no more left work on the ressource. But this time, we can see there is real work reported but not for the assigned ressource... 

Attachments:

Please Log in or Create an account to join the conversation.

More
03 Feb 2021 18:25 #3 by louisc
Replied by louisc on topic Unfound left work on a task
Hello,

I finally found where was the left work. It was in meetings that were not closed.
Not a bug, I close the issue.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.180 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.