Real Work Imputation not working

More
15 May 2021 02:50 #13 by mika095
Yes the issues is about resources, not activities.
I forget to tell that the peoole (ressources) that cannot charge activities they are assign for can charge the tickets they are assign for.

what do you suggest ?

Tks

Please Log in or Create an account to join the conversation.

More
17 May 2021 17:26 #14 by babynus
I really cannot understand where it comes from.

We should find what is specific with these users, characteristics that they share in common that they don't share with other users.
  1. Do they have a specific profile ?
  2. Do their allocation to projects have some specificity ?
  3. Do they use varying capacity or overbooking ?

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
17 May 2021 17:46 #15 by babynus
To try and debug :
Save file /model/ImputationLine.php.
Install attached patch (unzip like a new version).
Set debug level to 3 (debug) in Admin page.
Display timesheet with issue.
Reinstall saved ImputationLine.php file
Set debuglevel back to 2 (trace)
Post log file (part when Timesheet is displayed) here.
 

Babynus
Administrator of ProjeQtOr web site
Attachments:

Please Log in or Create an account to join the conversation.

More
19 May 2021 12:26 #16 by mika095
Tks I wil try this and come back asap

Please Log in or Create an account to join the conversation.

More
27 May 2021 16:17 #17 by fsouliers
Hello,
just in case : do those people have projects that are "under construction" that appear in the beginning of their timesheet ?

I think I already saw that : one project displayed at the very beginning of the timesheet was "under construction" so all the timesheet was locked (we quickly solved it by changing the wbs level of the project causing the problem)

Hope this helps
The following user(s) said Thank You: tblanken

Please Log in or Create an account to join the conversation.

More
07 Jul 2021 12:15 #18 by tblanken
I can confirm that this erroneous state occurs under described circumstances.

In our case we had a ticket, linked to a deleted project (and so a deleted activity also) which blocked the ability to enter worktime. In addition, there was an entry of abou 174 hours booked in ticket on 18.06.2021).
The formular was disabled from the past to a concrete date (e.g. until 18.06.2021).

Steps to correct the erroneous state:
1. Removed project & activitity form ticket via database
2. Changed ticket-state from closed to re-open
3. Corrected wrongly entered hours spend on ticket
4. Changed ticket-state from closed to closed

Best regards,
Torben

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.045 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.