ProjeQtOr free project management software - [SOLVED] Cost and Works left work error - ProjeQtOr
 

[SOLVED] Cost and Works left work error

More
03 May 2021 15:10 - 03 May 2021 15:12 #1 by karl.binet
Hi,

V9.1.3

In a activity I have incorrect value in Cost and Work Assigned Work 137h - Real 41.25 total 95.75h but left works shows 115H



I'm having this issue in other project/activities.

I did he Fix Issues in consistency checks, did not change anythings

Any hint on how to solved this issue 

Regards
Attachments:
Last edit: 03 May 2021 15:12 by karl.binet.

Please Log in or Create an account to join the conversation.

More
04 May 2021 18:27 #2 by babynus
IT is not an error.
It is just that resource changed Left work to point out he will not finish on time.
Left is not always Assigned - Real (otherwise we yould not need reassessed)

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: karl.binet

Please Log in or Create an account to join the conversation.

More
05 May 2021 19:30 #3 by karl.binet
Great, i understand, i looked at all the activities attach to this one and i found an activity that hours were manually added.

Thanks

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 2.576 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.