We have a problem exporting and reopening a project (gantt) from Projeqtor.
The duration of the tasks don't match.
Example on the first 2 tasks on battached pictures :
- 'Input data definition ' task : 3 days on Projeqtor goes to 0.6day on MS project.
- "Product design" task : 20 days on projeqtor goes 4 days on MS project.
Have you ever seen this issues? Do you have a solution to are able to open the datas on MS project with the correct task durations.
I guess it is because MS-Project does not manage Pools.
Moreover, you are using a "unique resource" planning for the pools.
MS-Project does not understand and uses full pool capacity...
This is a limit of export/import with tools than don't plan the same way.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.