ProjeQtOr free project management software - Planning xml export => tasks transformed to milestones - Page 2 - ProjeQtOr
 
 

Planning xml export => tasks transformed to milestones

More
27 Oct 2021 16:48 - 28 Oct 2021 16:52 #7 by LaurentC
In your demo database, project PPS01:
Export the planning in MS Project xlm leads to the attached result.
Seems to be a problem with task duration.
The duration exported format is not correct: should be an integer: (see docs.NotAllowedScript617ab919e0205micros...=project-client-2016)
<DurationFormat>
IntegerValue
</DurationFormat>
Exported: <Duration>PT8H0M0S</Duration>

Thanks in advance
#L.
 
Attachments:
Last edit: 28 Oct 2021 16:52 by LaurentC.

Please Log in or Create an account to join the conversation.

More
29 Oct 2021 11:16 #8 by babynus
Hi,

There is no issue with <DurationFormat> tag : if always contain an integer (7 ou 21)
tag <Duration> is then not an integer, as it depends on DurationFormat

What is strange is that when I open the xml with MS-Project 2019, all is fine, I mean I get same planning as on projeqtor.
 
So is it difficult to tell if it is a projeqtor issue or an MS-Project issue ?


 

Babynus
Administrator of ProjeQtOr web site
Attachments:

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.039 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.