Client Contract - Tokens management - Modification

More
06 May 2022 18:06 #7 by AMAZ
Hello,

I have found 2 more bugs like these :

- When I import activities with .csv files, "validated work" is multiplied by seven during importation.
- In meetings, when I select the date and hour, then assign someone to the meeting -> the automatic assigned work is the duration of the meeting multiplied by 7.

Is it linked or is it something else that needs its own topic ?

Thanks,

Best Regards,

Anaïs

Please Log in or Create an account to join the conversation.

More
07 May 2022 12:19 - 09 May 2022 09:51 #8 by babynus
In import file, Work is expected in Days.
I guess you defined 7 hours per day/
So if you import data entered in hours (2), the amount is stored as days (2 days), so display after import is 14 hours

Babynus
Administrator of ProjeQtOr web site
Last edit: 09 May 2022 09:51 by Arkhanje.
The following user(s) said Thank You: AMAZ

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.038 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.