Hi team,
In the resource costs per month, without any resource selected and without any month selected (=> all resources on one year):
Blue bars = planned + real => what is the interest? => The real values should be used in place of real+planned.
Black line: should be the cumulated value of blue bars, but is not.
If you edit the report in the middle of the month, you'll have have the month as Real work, and the other half ar Planned work.
You may also have some real work in the future (for holidays)
Thanks for your reply,
I understand what you're explaining, but still no catch the interest of [planned+real] blue bars.
And the cumulative black line is false, unless I'm wrong ?
Best regards
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.