hello
we are in version 12.02 we noticed that in multiple case when we create a ticket associated to a planning activity. the ressources updates the real work on the ticket for examle for 1 day than in the planning activity projeqtor automaticly updates real work for the ressource to another value usually very big number such as 200 Man day in the planning activity or 40 man day and the real work on the ticket is 1 day or 3 days. This value is in grey in the planning activity assignation.
All the reports and KPI reflect this incorrect situation such as project dashbord , charges KPI ... The only the report that reflects the real values is the report for real work per ressource.
Thank you for your help and assistance
Hello,
Thank you for your reply.
please find the details
there is one ticket ( ticket 54 : parsing of office 365) , this ticket is associated to an activity planning with the same name.
the ressource works and updates real work on the ticket total reel work on the ticket is one day.
in the report of detailled charges per activity we see one day for the activity parsing of office 365 which is normal as it is the activity planning of the ticket 54 ( parsing of office 365 ) as it reflects the reel work updated on the ticket linked to it as this ticket is synchronized with the activity of plaaning.
When we go to the assignation section of the task parsing office 365 we see assigned day = zero this is because this assignation comes from the synchronized ticket which normal but Unfortunatly the reel work is 35,7 days this have been done by projeqtor it self as the ressource did updated the reel work only in the synchroniozed ticket associated with this activity of planning.
Also the project reel work in the section projects is also affected by this bevaviour and mentions a total days that include the not correct 35.7 days this is also reflected in the report KPI of charges but all the other reports of reel work show the coorect value of the reel work as it is mentioned in ticket : one day.
thank you for your help and assistance
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.