"exclude from planning and purge current planned" doesn't work anymore

More
21 Nov 2025 07:48 #1 by RoBra81
Hello,

following issue: since version 12.3.2 behaviour of "paused - exclude from planning and purge current planned" within activities changed. In former versions planned date was deleted when setting paused. Since version 12.3.2 planned date stays as calculated and will never be change. In my opinion former behaviour was better.

Thanks in advance
Ronny

Please Log in or Create an account to join the conversation.

More
02 Dec 2025 13:38 - 02 Dec 2025 13:43 #2 by maxca
Hello,
It seems that this is a bug. Ticket recorded #10827
Have a nice day,
 
Last edit: 02 Dec 2025 13:43 by maxca.

Please Log in or Create an account to join the conversation.

More
12 Dec 2025 15:45 #3 by babynus
Hi

This was suggestion from our Qlub of users : when item is "paused", last planned dates should be preserved.
It is just "paused", not purged.

But planned work is purged so that availability of resources is not used by pauses items.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.041 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.