Hello,
I would like to change the daily rate of a resource within one project and activity, to account for pay rise during projects that sometimes have a lifespan of more than 2 years. My version of Projeqtor allows only for 1 daily rate per resource per activity, and it is locked for the remainder of the project duration. How can I find a way around this ? Thank you
A resource can have cost than change during tilme.
In the resourece screen, enter value for same role / function, you'll have to enter start date for the new resource cost.
The costs will automatically be updates :
real cost = real work * cost at the corresponding date (calculated day by day)
left cost = real work * new cost
Assigned cost = assogned work * cost at date of assignment creation
Note that if you want to update a cost only for a given project you can define a cost for the resource for a new role / function, then change role / function on the assignments for this project. This last update can be done through Multiple update on screen Assignement (available on V12 but not in your current instance version)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.