I might have found a problem. In order to import huge set of activities from CVS file, I truncated Activity, Planningelement, dependency, work and assignment tables.
As ALTER TABLE activity AUTO_INCREMENT=0 didn’t work for me, truncate was an easy way to get id(s) cleaned. I wanted to start from 0 because I’ve already got a set of data with id and parent id starting from 0.
Import was great until I found that the WBS was weird at a certain point. I reproduced the problem with 2 tasks.
I assume that’s because of my Truncate, but it’s doesn’t seem normal to me.
No,
WBS should never be null.
But WBS for activities should never be 1.
Exemple :
1 => Project 1
1.1 => Task of project 1
1.2 => SubProject of project 1
1.2.1 => Task of SubProject of project 1
1.2.1.1 Sub task
1.2.1.2 Other sub-tack
and so on...
Ok, so if WBS for project is 3. Your example would be ?? :
Exemple :
3 => Project 1
3.1 => Task of project 1
3.2 => SubProject of project 1
3.2.1 => Task of SubProject of project 1
3.2.1.1 Sub task
3.2.1.2 Other sub-tack
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.