ProjeQtOr free project management software - Activity left time, calcul is not correct - ProjeQtOr
 
 

Activity left time, calcul is not correct

More
29 Aug 2014 15:11 #1 by jeda
This issue arises in one activity:

assigned work=20
real work=1,07
left work=3650,93 (this calcul is automatic)
Attachments:

Please Log in or Create an account to join the conversation.

More
29 Aug 2014 22:29 #2 by babynus
Hi,

Could not reproduce.
Most likely is an update of left work by resource who entered real work (left work can be changed there)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.030 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.