Hi !
I've got a question on "work synthesis by activity" report : Due to conversion day > jours, 12H validated work defined on activity is displayed as 11.98h in report. Is it possible to change this ? For information, my company's day = 7.35 hours

Thanks for your answer.
Regards
Last edit: 28 Nov 2014 08:34 by protion.
The topic has been locked.
More
27 Nov 2014 22:18 #2 by babynus
Replied by babynus on topic Values rounding in reports
Ticket #1623 recorded.
Not sure this rounding issue can be fixed with a default day of not round hours.

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.030 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.