01 Jul 2015 19:57 #1 by francis2301
Hi,
I have a alert which is currently with "CLOSED" status for activities. However, when I import activities from MSExcel, using projeqtor import functionality, the e-mail warning/alert for activities is generated (it seems that it does not considere that the alert status is "closed").

The alert was generated for a few activities which were created (via xls import) with "validated start date" = "29-jun-2015" and "validated end date" = "03-jul-2015".


My alert is configured as below:
- item: activity
- related to validated end date
- warning: 10 days
- alert: 3 days
- status: closed
- send e-mail to: responsible and project manager


Kind regards.
Francis

Please Log in or Create an account to join the conversation.

More
03 Jul 2015 15:42 #2 by babynus
Issue confirmed.
Ticket #1758 recorded.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: francis2301

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.