ProjeQtOr free project management software - [v6.0.1 acceptance review] - reference planning to fix - ProjeQtOr
 
 

[v6.0.1 acceptance review] - reference planning to fix

More
30 Nov 2016 19:27 #1 by VERGES
In same way of 45° curve , it would be possible to fix the reference planning at T0 of the projet before "today date".

Validated workload shall be fix in the past ...

Please Log in or Create an account to join the conversation.

More
01 Dec 2016 12:39 #2 by babynus
This is not an issue with 45° grash but with baseline.
Already recorded as Ticket #2405

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
08 Dec 2016 15:37 #3 by VERGES
[Acceptance review 6.0.3] : Ok . Now is possible to fix a planning in the past. You're right, is not a 45°curve issue but a baseline configuration issue. To fix a planning in the past is possible only if there are not baseline already fix.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.