When autoplanning is not used (manual planning, so "left work"=0 or no resources assigned to tasks), it would be very useful to have the possibility to manually postpone several activities all together.
Otherwise, if you have a big Gantt and the overall project is postponed it's a nightmare to manually shift all the activities.
Drag and drop would be the best, but as a workaround you could set that the user can use the already present feature to modify several tasks together, and symply write "+ number of days" in the dates that have to be modified.
Like Start date = "+5".
So that all the selected tasks get updated relatively to their initial start date.
The easyest it to do it the right way.
Instead of planning with fixed dates, only pla with fixed furations.
Just add expected fixed milestones (start) and floating milstaones (delivery) and dependencies..
Then you'll just have to change the first milestone start date to have all your planning switched.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.