I don't understand the need behind this.Allow the selection of several activities for resources. For example, in the "resource" view, use the "Detail element of list" and allow the selection of multiple activities
Not planned (quite complex to display)1) PERT view
Ticket #433 already exists.Identify the critical tasks (more risky) => Critical Path
Good idea. Ticket #866 recorded.When one selects one activity (visible on the window bottom), and we pass the mouse on the window at the bottom, you can not see where we are on the gantt view. => It would be nice to maintain the color line being displayed
I don't understant. Could you explain ?If tickets are related to an activity must be linked estimated work, real work and the RAF
When one selects "planning activity " should be automatically to linke Ticket and activity
Please Log in or Create an account to join the conversation.
Yes I would simplify resource allocation has several activities. My idea is to use the "Detail element of list"I don't understand the need behind this.
Of course you want to have a quick assign method, but why from resource view ?
I would like to link tickets to activities. worload, real work and ledft work must go back to the activities if they are related. This would allow the resources to work on tickets for evaluating the left work.I don't understant. Could you explain ?
Please Log in or Create an account to join the conversation.
Could you please detail the real need behind this request. It is not a standard way (to my opinion). Usualy, manager defines activities and then assigns resource to each activity, not the other way round.Yes I would simplify resource allocation has several activities. My idea is to use the "Detail element of list"
Is is almost what is done with Planning Activity, except to the management of left work. You can have a look to the user manual to get more information. Maybe a different or completed way to check left work on tickets could be an improvement.I would like to link tickets to activities. worload, real work and ledft work must go back to the activities if they are related. This would allow the resources to work on tickets for evaluating the left work.
An idea: Assign tickets as assigned resources but load consumed and RAF will those ticket
Please Log in or Create an account to join the conversation.
I completely agree with your vision.Could you please detail the real need behind this request. It is not a standard way (to my opinion). Usualy, manager defines activities and then assigns resource to each activity, not the other way round.
Ok I'll try. I thought that when you connect the activity with 1 ticket and we changed the load allocated or consumed, the activity was not modified (workload allocated or consumed)Is is almost what is done with Planning Activity, except to the management of left work. You can have a look to the user manual to get more information. Maybe a different or completed way to check left work on tickets could be an improvement.
Please Log in or Create an account to join the conversation.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.